A. Columns and beams shall have heliarc welded endplates and concealed connectors.
B. The canopy deck is to have welded end closures at the deck terminations.
C. The canopy shall be fabricated to drain through the columns.
D. Flashing shall be .040 aluminum fabricated to prevent leakage between the canopy and adjacent structures.
A. Install the canopy in strict accordance with the manufacturer's
recommendations.
B. Erect canopy after concrete and masonry work in the vicinity is completed and washed down.
C. Install columns and beams straight and true.
D. Install raincaps over draining sections of the deck.
E. Fill downspout columns with grout to discharge level to prevent standing water. Deflectors should be installed after grouting.
F. Install flashing as required.
G. Thoroughly clean canopy after installation